ASSESSMENT OF THE EFFECT OF MAINTENANCE IN BUILDING
SUSTAINABILITY
BY
IWUAMADI EMMANUEL CHIJIOKE
2018/118581
DEPARTMENT OF BUILDING
FACULTY OF ENVIRONMENTAL STUDIES
ABIA STATE UNIVERSITY UTURU
MAY, 2024.
2
ASSESSMENT OF THE EFFECT OF MAINTENANCE IN BUILDING
SUSTAINABILITY
BY
IWUAMADI EMMANUEL CHIJIOKE
2018/118581/REGULAR
A PROJECT SUBMITED TO THE DEPARTMENT OF BUILDING
FACULTY OF ENVIRONMENTAL STUDIES
ABIA STATE UNIVERSITY, UTURU.
IN PARTIAL FULFILMENT OF THE REQUIREMENTS FOR THE
AWARD OF BACHELOR OF SCIENCE (B.Sc) DEGREE IN
BUILDING
SUPERVISED BY PROF DAVID O. ONWUKA
MAY, 2024
3
APPROVAL PAGE
This is to certify that this project was done by IWUAMADI EMMANUEL
CHIJIOKE with the mat. No. 2018/118581/REGULAER that to the best
of my knowledge, this is the original work of the candidate, and the project is
accepted in partial fulfillment of the requirements for the award of the degree
of Bachelor of science (B.Sc) in Building.
………………………………….. …………………..
Prof David O. Onwuka Date
(Supervisor)
.................................. ....................
Bldr Dr. Oscar Onumadu Date
(HOD)
................................... .....................
Prof. G.C. Alozie Date
(Dean)
.................................. .....................
Date
(External Examiner)
4
DEDICATION
This research work is dedicated to God Almighty and to Iwuamadi’s family.
5
ACKNOWLEDGEMENT
In the course of writing this research work, I received lots of
encouragements, assistance and help from various sources.
First and foremost, I wish to thank Prof David.O. Onwuka my supervisor, the
head of department building technology Bldr Dr Oscar Onumadu, Prof G.C.
Alozie (Dean), Engr. Grant Onwuka, Bldr Richard Maduka, Bldr Obinna
(Academic advisor) etc, for the assistance and encouragement they gave me.
Also I am grateful to all my lecturers Prof David O. Onwuka, Engr. Grant
Onwuka, Bldr Richard Maduka, Bldr Dr Oscar Onumadu and many others for
their invaluable contributions. I also wishes to express my appreciation to my
colleagues and friends for their support throughout this program; the Men of
Integrity (G5), Chukwu Ifeanyi, Uche Obinna, Omar Better, Okafor Mercy,
Emmanuel Blessing Adaeze and others.
It won’t be complete without mentioning my parents Chief Elder A.O.
Osuagwu and Deaconess mother Grace O. Osuagwu, my Siblings, Dede
Maira, CJ Enterprises, Genma Constructions Nigeria and many others.
Lastly, I appreciate the Authors of many excellent text books, journals,
lecture notes that guided and influenced the writing of this work.
My greatest gratitude goes to the Almighty God, the Author and finisher of
my faith. Without Him, I wouldn’t have gone this far in life.
6
TABLE OF CONTENT
Cover Page i
Title Page ii
Approval Page iii
Dedication iv
Acknowledgement v
Abstract vii
CHAPTER ONE: INTRIDUCTION
Background of the study 1
Research problem 2
Aims and objectives 3
Significance of the study 3
Research questions 4
Hypothesis 4
The scope of the study 5
Limitation of the study 5
CHAPTER TWO: REVIEW OF RELATED LITERATURE
Conceptual framework 6
The concept of maintenance 8
The coverage of maintenance 8
Objective and goals of building maintenance 9
Types of maintenance 14
Planning of maintenance work 16
Maintenance programming 18
Permit for maintenance 19
7
Causes of maintenance problem 20
Design components for maintenance strength 22
Lack of integration of construction processes 26
Maintenance management 27
Planning 28
Summary of Review of Literature 29
CHAPTER THREE: RESEARCH METHODS
Research design 30
Population for the study area 30
Sampling technique 30
Sampling population and sample size 31
Method of data collection 31
Instrument for data analysis 32
CHAPTER FOUR: RESULTS AND DISCUSSION
Results 34
Hypothesis testing 39
Discussion of result 41
CHAPTER FIVE
Summary 43
Recommendation 43
Conclusion 45
8
ABSTRACT
Building maintenance is commonly known or includes cleaning common areas, removing
trash regularly and repairing items that are broken. It also involve inspecting, repairing
and maintaining electrical systems, heating and air conditioning systems and other utility
services.
This research work is done using a quantitative method because it deals with numeric
data.
Data were collected from field workers and it’s presented and analyzed in chapter four,
they were analyzed using pie chart, histogram, percentage etc. Data were collected from
the occupants of Ikenegbu layout, comprising of those in residential buildings and in the
commercial building. There were total of 40 respondents of which the landlords and
tenants were 25, including banks and fast food restaurants.
Adequate maintenance roles ensures safety of the building, inhabitants of the building and
the environment in general, Maintenance also assures quality control in order to safeguard
attractive environment (building), and enhance sub-standard ones.
This does not only resolve maintenance problems, but tries to reduce the cost of operative
and services.
Efficiency of operations is derived through adequate maintenance. Thus, this enhances the
comfort of the building of the users. Maintenance also assure structural integrity (i.e. the
building can stand any further reconstruction), protection, compliance with environmental
regulation, containment and even the appearances of the building.
Based on the findings of this study as outlined in the preceding chapter, and also
anticipate problems that may be faced on the maintenance of buildings, the following
recommendations are seem deemed and advisable for the realization of the aims and
objectives of such buildings.
i. In order to improve the attitude of Nigerians as a whole towards the role of
building maintenance, a result oriental public awareness campaign is necessary
so as to intimate the public with the benefits desirable from a well organized
routine preventive building maintenance system. The campaign could be in the
form television slots, normal private conversation and service to client by
professionals.
ii. The government should look seriously into the possibility of establishing a
national board for protection and maintenance of public and private buildings.
iii. Property owners should also follow suit by making sure that their properties are
properly managed, protected and adequately maintained by trained individuals
in these various fields.
iv. The various professionals in the building industry have a big role to play in the
cause of rendering professional service to help the building maintenance
manager work properly and smoothly.
This research work was based on the sustainability of buildings as regards to
maintenance, taking its care study from Owerri.
9
CHAPTER ONE
INTRODUCTION
1.1BACKGROUND TO THE STUDY
Building maintenance is a major activity in the construction industry, though
with the low rate of maintenance work, almost the total output of the
construction is devoted to this activity as it aims to update and sustain
existing structure to contemporary standards. Maintenance starts immediately
after the completion of a building and should be planned at the design stage,
so as to arrest any structural defect before it mature in its liability period and
beyond. It is important to note that it is practically impossible to produce
buildings that are maintenance free, Maintenance of buildings in Nigeria and
in the building industry, has been neglected, as little or no attention is giving
to it by the building owners and the property developers.
In Nigeria, most professionals never thought of maintenance when
designing buildings, instead, they always point accusing fingers at one
another and mostly tenants, landlords, maintenance personnel, as well as
weather condition and natural calamities when buildings fail. It is known that
maintenance objectives, are primarily to preserve buildings in their initial
functional, structural and aesthetic states. This is to ensure that they
continue to remain in such states and retain their investment value over a
long period of existence. However, looking into our buildings in Nigeria, one
notices and array of abandoned and epileptically functioning facilities. Though
many theories and hypothesis are postulated daily on building issues and
10
especially on building maintainability, maintenance problems remain
unaddressed and unresolved.
A good maintenance role is essential to the health, safety and well-being of
any community. Unless a community has well maintained buildings and
workable planning system, among other things, improved social, economic
expansion will be difficult, if not impossible to achieve and sustain. Over the
past years, maintenance has been a very big problem, maybe due to large
increase in the number and variety of physical assets, which must be
maintained and the changing views on maintenance and repairs. At the same
time, the limitations of maintenance systems, are becoming increasingly
apparent, no matter how much they are computerized. In the face of
avalanche of changes, managers, landlords, property developers, tenants,
maintenance personnel are looking for a new approach to solving
maintenance problems.
1.2 STATEMENT OF THE PROBLEMS.
Ensuring that building are preserved in their initial functional, structural,
and aesthetic states, designers, engineers, e.t.c, are lead to a better
understanding of the functionality of these buildings. Achieving these basic
functional requirements, which are according to Moubry John (2012)
maintenance problems, results in asking of question such as:
(i) How can the most appropriate techniques be selected?.
(ii) How can all the expectations of the owners of the assets, the
users and the society be met?.
(iii) How can one work in the most cost effective fashion
(iv) How can the active support and co-operation of all the sectors
involved be secured.
11
1.3 AIM AND OBJECTIVES OF THE STUDY
Aim of the study;
The aim of this research is to assess the roles of maintenance in building
sustainability and this aim will be achieved with the following objectives they
are;
(i) examine the present practices and problems of the maintenance
of building in Owerri so as to determine their sustainability.
(ii) assess the challenges in the existing maintenance system that
affected maintenance of building.
However, the primary aims of maintenance is to ensure that building
continue to perform in a reliable useful way, which includes; good
appearance (aesthetics). Continuity of function, retaining value on
investment. These aims are achieved through the purpose of this study
which assesses the level of role of maintenance in building sustainability
with reference to buildings in Owerri.
Above all, the goal should be to maintain each building regularly to a
standard which will carry the building through one repair cycle to another.
1.4 RESEARCH QUESTIONS.
(i) What are the present practices and problems of maintenance? That
affects the sustainability of buildings.
(ii) What are the existing maintenance systems weakness and
inadequacies that affected the maintenance of buildings in Owerri
12
(iii) What are the influences of the negligence of maintenance on buildings
and their occupants.
(iv) What are the measures/polices to be taken towards effective and
productive maintenance management efficient?
(iii) What are the measures necessary for an effective maintenance
Role as a means of sustainability in building?
1.5 HYPOTHESES.
The following hypothesis provides the basis for the test;
Ho: The present maintenance practice and it’s problems has significant effect
on the sustainability of buildings
Ho: The challenges of existing maintenance systems affect significantly the
maintenance of buildings in Owerri
1.6 SIGNIFICANCE OF THE STUDY.
Adequate maintenance roles ensures safety of the building, inhabitants of the
building and the environment in general, Maintenance also assures quality
control in order to safeguard attractive environment (building), and enhance
sub-standard ones.
This does not only resolve maintenance problems, but tries to reduce the cost
of operative and services.
Efficiency of operations is derived through adequate maintenance. Thus, this
enhances the comfort of the building of the users. Maintenance also assure
13
structural integrity (i.e. the building can stand any further reconstruction),
protection, compliance with environmental regulation, containment and even
the appearances of the building.
1.7 SCOPE OF THE STUDY.
The research works in encapsulates all the areas of maintenance which
includes the types of maintenance necessary to handle all the maintenance
problem arising from the case study. This research work is limited to Owerri,
of which 70% of its occupants are civil servants, who are middle class
citizens. Most of the buildings, especially those in old Owerri, consist the
oldest buildings in Owerri, requiring maintenance at the present area. The
maintenance of these buildings will be of interest, due to no adequate plans
for maintenance where made as already drawn plans were brought and was
shared to anyone capable of building.
1.8 LIMITATION OF THE STUDY
This research was hampered to an extent by time and getting the
respondents for the oral interview was also a problem. This was as a results
of lack of time on their own side according to some of them. But with added
effort from both parties, this research was successful.
14
CHAPTER TWO
LITERATURE REVIEW
2.1 CONCEPTUAL FRAMEWORK.
There are many definitions of maintenance. The British standard
(BS) 3811: (1984) defined maintenance as; “the combination of all technical
and associated administrative actions intended to retain an item in, or restore
it to a state, which it can perform its required function”.
According to Obodoh (2012) “maintenance is said to be work undertaken in
order to keep, or restore or improve every facility, i.e., every part of the
building, its services and surrounding to a currently acceptable standard and
sustain the utility and value of its facility”. From the above, the words in the
definition, according to Obodoh (2012): keep-work carried is out in
anticipation if failure (preventive); restore-work carried out after failure
(corrective) and Improve – work carried out to elevate the standard or
change its present purpose (reconstruction).
He went further to say that maintenance is work carried out to retain the
functions of a facility to an acceptable standard. The phrase, acceptable
15
standard refers to that condition or state of a building, acceptable to the
person receiving the benefit, to the public at large or specified section of the
public. Standards are improved, it may be higher or lower than the initial
design, but however, buildings are modified to accommodate new uses.
From the engineering view point, there are two elements to the management
f any physical asset, (a.) must be maintained, (b) from time to time there
may also be need to be modified.
The major dictionaries, defined maintenance as “the cause to continue”
(oxford) or “keep in an existing state”. This suggests that maintenance
means preserving something. On the other hand it is agreed that to modify
something means to change it in some way. However, this study focuses in
maintenance at this point. Moubray (2012) stated that maintenance is
ensuring that physical assets e.g. buildings continues to do what their users
wants them to do. When one sets out to maintain something, there are two
questions that readily come to our mind (a) what is it that the user wants to
cause to continue? (b) What is the existing state that requires preservation?
The answer to these questions can be found in the fact that every physical is
put into service because someone wants it to do something. In other words,
they expect it to fulfil a specific function or functions.
So, it follows that when one maintains an asset, the state one wish to
preserve, must be one in which it continues to do whatever its users want it
to do. The technology of maintenance according to Seeley (2014) explain
that maintenance seeks to preserve a building in its initial state, so that it
continues to serve its purpose, and it’s an essential component in the life
cycle of a building. The construction field is particularly prone to lose
interpretations, which to Seeley (2014) defines maintenance as all
construction works other than new capital work undertaken to keep a
16
building in a satisfactory state of preservation. Preservation in this definition
does not only apply to buildings alone, but also the health and safety of
occupants and to the environment including the community. To that effect
Milton (2015) stated that it implies that components, have to be put in that
same condition as they were when they was first put to use.
This is most arduous burden to place on upon a user, but on it is essential for
the health, safety and well being of the occupants, those outside the building
and to the environment, who could be affected by the catastrophic loss of
containment.
Maintenance management as defined by Allyson (2015) is the selection of the
goals procurement, organization and the control of necessary resources for
their achievement. Management is concerned with the dynamic of
circumstances and activities, and it is general motivated by the need to
economize the use of resources and time in achieving predetermined
objectives.
2.1.1 THE CONCEPT OF MAINTENANCE.
Building maintenance is one of the major components of a buildings life
cycle. The full cycle is categorized into the following.
(i) Conceptualizing a new project (design)
(ii) Project implementation (construction)
(iii) Maintenance (sustaining the utility)
(iv) Obsolescence ( run down stage)
It is obvious that the above stages are interwoven. However, the action
which take place in the first stage have great effect on maintenance stage.
For example, the effectiveness of design, choice of quality standard in
terms of specification and assembly, the care taken in the use of the
17
facility, exposure of circumstances, etc affect the status of maintenance.
Andrew (2019) stated that maintenance therefore, is designed to the
conditions of the facilities and keep it in a sustainable when still in use.
2.1.2 THE COVERAGE OF MAINTENANCE.
Maintenance as a service covers every aspect of building environment,
particularly the buildings assets and infrastructural facilities. Such facilities
spread across the project in several sectors of the economy which includes
agriculture, commerce, energy, building construction, environment, defence,
etc. The spread also extends to social sectors such as roads, electricity,
telecommunications, etc. It is a note worthy that such project has implication
for regular maintenance for sustainability.
2.1.3 OBJECTIVES AND GOALS OF BUILDING MAINTENANCE.
According to Bamisile (2020), the major objectives of building maintenance
are;
(i) To ensure that the functional requirements of the facility are
attained at all times.
(ii) To create conducive and a tenable accommodation for owners
and occupants.
(iii) To enhance the quality of the building structure to meet modern
requirements.
(iv) To prolong the life span of the buildings.
(v) To preserve the physical characteristics of the building and
associated so as to reflect fewer breakdown and thereby reduce
the probability of early failure.
(vi) To ensure that assets are kept at reasonable standard and at
least cost.
18
(vii) To maximize the economic and financial returns from the use of
the building.
Most people become engineers, because they feel at least some affinity for
things, be it mechanical, electrical, civil or structural. This affinity leads
them
to derive pleasure from assets that are in condition, but to feel offended
when assets are in bad condition. These reflexes have always been at the
heart of the concept of preventive maintenance.
They have given rise to concepts such as assets care which as the name
implies seeks to care for assets per se. They have also led some
maintenance strategist to believe that maintenance is all about preserving
the inherent reliability or built-in capability of any asset. In fact, this is not
so. This emphasis on what the asset does rather than what it provides is a
whole new way of defining the objectives of maintenance for any asset.
According to Roy (2018) states that one must gain a crystal clear
understanding of the function of each asset together with the associated
performance standard, by asking question like; what are the functions and
associated performance standard of the asset in its present operating
standard context? Moubray (2012) opines that the objective of
maintenance is to ensures assets continues to do what their users wants
them to do. He went further to say that the extent to which any user
wants the asset to do something can be defined as the maximum
performance without deteriorating in anyway, then that will be the end of
the matter. This means that when any asset is put into service, it must be
able to deliver more than minimum standard of performance desired by
the user. This means that performance can be defined in two ways; (a)
desired performance [what the user wants the asset to do], (b) built-in
19
capability [what the asset can do]. Maintenance helps to ensure that asset
continue to fulfil their intended functions, either by ensuring that their
capability serves the minimum standard desired by the user or by
restoring something approaching the initial capacity and by how it is
made. (d) Maintenance can only restore the asset to this initial level of
capacity, it cannot go beyond it.
INITIAL CAPABILITY (What the asset can do)
Figure 2.1 A maintainable asset (reliability-centred maintenance)
Source: Moubray, 1
Maintenance
cannot raise the
capability of the
asset above this
level
The objective of
maintenance is to
ensure that capability
stays above this level
Maintenance achieves
its objectives by
maintaining the
capability of the asset in
this zone
DESIRED PERFORMANCE (what the user wants the asset to do)
The objective of
maintenance is to
ensure that the
capability stays above
this level
Maintenance cannot
raise the capability of
the asset above this
level, so it is not
maintainable
20
Figure 2.2: A non maintainable asset (Reliability-centred Maintenance)
Source: Moubray, 2012
Two conclusions which can be drawn from the above examples are that:
(a) For any asset to be maintainable, the desired performance of the
asset must fall within the envelope of its initial capability.
(b) In order to determine whether this is so, one only need to know the
initial capability of the asset, but one also need to know exactly what
minimum performance that user is prepared to accept in the context
in which the asset is been used.
This outlines the importance of identifying precisely what the user want
when starting to develop a maintenance program.
According to Obodoh (2012), the primary aims of maintenance are:
(a) Good appearance of the building, which includes the natural and
ratification beauty of any facility, maintaining the facility so that it is
pleasing to the eyes. The maintenance of buildings ensures good
appearance to the public.
(b) Continuity of function is the responsibility of an individual or group of
individual to maintain an existing building so that its function is
retained. This means maintaining the building in a condition in which
it continues to fulfil its required functions.
(c) Retaining value on investment is the desire of any building to retain
value of money invested on it. To achieve this, the building requires
maintenance in order to justify the investment. In a case where the
21
house owner fail to maintain the building or maintain it themselves
and deduct the cost from their rents.
According to Iwuanyanwu (n.d), the rationales for maintenance are;
(a) To maintain to an acceptable quality standard particularly to existing
structural fabrics and facility which meets current taste demands.
(b) To raise the quality of life existing facilities which have fallen below
existing taste and demands.
(c) To prolong the lifespan of a building particularly at a time when the
cost of new projects are escalating due to inflation and in the phase
of shortage of funds for construction.
(d) To upgrade as in renewal, particularly where existing have
deteriorated beyond what moral repairs and maintenance can
rectify.
(e) To attract higher rental income particularly evident on conversion of
residential accommodation into offices and shops where feasible.
Obodoh (n.d) in his own viewed, gave the following as major
objectives of building maintenance;
(a) To ensure that the function requirement of the facility is attained at
all times.
(b) To create a conducive and tenantable accommodation for owners
and occupants or users.
(c) To enhance the quality of building structure to meet modern day
requirements.
22
(d) To prolong the life span of the building.
(e) To preserve the physical characteristics of the building and
associated services so as reflect fewer breakdown and thereby
reduce the probability of early failure.
(f) To ensure that asset are kept at a reasonable standard and at least
cost.
(g) To maximize the economic and financial returns and from the use
the building.
(h) To ensure the safety of the occupants.
2.1.4 TYPES OF MAINTENANCE.
The British standards BS: (1998) divided maintenance into planned and
unplanned maintenance.
Planned maintenance was further divided into preventive and corrective
maintenance. The planned preventive maintenance is the work directed to
the prevention of failure and is carried out within the expected life of the
facility to ensure its continued operation. This is done at predetermined
interval during the expected life of the building. The planned corrective
maintenance is work performed to restore a facility or improve on its
operation to an acceptable standard. This is work carried out after the
breakdown of the facility. Seeley (2014) categorizes building maintenance in
the following terms and definition;
(a) Planned maintenance: The maintenance organized and carried
out with forethought, control and the use of records of predetermined
Plan.
(b) Unplanned maintenance: The maintenance carried out at
predetermined plan.
23
(c) Preventive maintenance: The maintenance carried out at
predetermined intervals or corresponding to prescribe and intended
to reduce the probability of failure or the performance degradation
of an item.
(d) Corrective maintenance: The maintenance carried out after the
failure has occurred and intended to restore an item to state in
which it can perform it required function.
(e) Emergency maintenance: The maintenance which is necessary to
in hand immediately to avoid serious consequences. This is
sometimes referred to as day to day maintenance, resulting from
such incident as gas leaks.
(f) Condition – based maintenance: The preventive maintenance
initiated as a result of knowledge of the condition of an item form
routine or continuous monitoring.
(g) Scheduled maintenance: The preventive maintenance carried out
at predetermined interval of time, number of operations, mileage
etc. Seeley (2014) further classified maintenance as:
(a) Major repair or restoration: works such as re – roofing or rebuilding
defective walls and often incorporating an element of improvement.
(b) Periodic maintenance: a typical example being annual contract for
decoration and the like.
(c) Routine or day to day maintenance which is largely of the preventive
type, such as checking rain water, gutter and serving mechanical
and electrical installations.
Speeding (2004) in his book, CIOB handbook of facilities management
showed two major activities in maintenance, namely response
maintenance and programmed maintenance.
24
Planned maintenance and programmed maintenance are synonymous and
are taken to mean the organization of work which has been initiated by
management, rather than by the tenant or client. Response maintenance
can be divided into normal maintenance and emergency maintenance;
these are categories which reflect the nature of the response rather than
the actual work done. For example, emergency work for housing is
normally carried out the same day the fault is reported.
Programmed maintenance can be categorized by two subgroups. First
preventive maintenance predetermined interval to minimize the probability
of element and components below required standards. Secondly cyclical
work, include painting and repairs prior to painting. Periodic maintenance
work consists of work done for health and safety reasons. Cyclical
maintenance can be categorized condition independent work, which is
work that is carried out at specific times irrespective of the condition of
the elements or components involved.
Preventive maintenance can also be categorized as condition-dependent;
the work should only be carried out when an element has reached its
optimum life span and where action is necessary to prevent further
deterioration of elements or components. Response maintenance is the
name given to the user of the property, normally the tenant.
The tenant is usually responsible for some of the minor and this will be
stated in the tenancy agreement. All other repairs are normally reported to
the landlord, or to the landlord’s agents.
2.1.5 PLANNING OF MAINTENANCE WORK.
Obodoh (2012) grouped planning maintenance work under the following
two systems namely.
25
i. Schedule/Budget system.
ii. Contingency system.
i. Schedule/budget system:
This covers items which tend to deteriorate at a more or less uniform
rate with no degree of urgency. This procedure takes the following
forms.
(a) Schedule work to be carried out at predetermined times. This applies
where incident of failure can be predicted with some accuracy or
where the periods are fixed by statue or contact for instance a house
requiring painting at fixed interval say every five years.
(b) Scheduling work to be carried out at predetermined times to prevent
failure or imminent failure. This is where the exact time of failure is
not known in certainty; hence inspections are carried to determine
whether or not the work is actually necessary.
(c) Scheduling work and inspection could be carried out predetermined
times. This applies where there is certainty in predicting that certain
work will be necessary at a particular time. Hence inspection is
necessary to determine the extent of any further work.
ii. Contingency system.
This entails a policy of waiting until the compliant is received from the user
before taking action. A necessary feature of this system is the need to
introduce a delayed period between receipts of the request and the actual
execution of the work. The main difference between scheduling and
26
contingency maintenance is that time between notification and execution
is greater for contingency system.
2.1.6 MAINTENANCE PROGRAMMING.
This is grouped into three major methods namely:
i. Long term programming;
This a major over haul of the property scheduled to take effect within a
long period of time say from ten years and above. It can scheduled by an
establishment to carry out maintenance work on a property for example
every ten years with the following purposes; (a) determining the general
level of expenditure on maintenance to achieve the desired standard.
(b) To avoid large fluctuation in annual items and any back-log (when
there are many work done).
(c) To determine the structural and staffing of maintenance organization
and whether it will be an advantage to employ operative directly to carry
out part or the whole of the work.
(d) To gear the maintenance programming to company policy so that it is
compactable with decisions relating to use of building.
(e) To consider the effect of proposed capital work on the maintenance
organization.
ii. Medium term programming.
This involves maintenance of a property annually. The object of the
medium or annual programming is to provide a more accurate assessment
27
of the amount of work to be carried out during the forth coming year and
to form basis for the financial budget when planning for the medium term
programming. Some of the considerations are:
(a) Timing the work in relation to the needs of the organization.
(b) Apportioning the amount included in the budget to specific jobs or
areas of work for control purpose.
(c) Fixing an appropriate time scale for the preparation of contract
document and tendering procedure where work is let to outside
contractors and for the advanced purchase of materials where the
work is to be carried out by direct labour.
(d) Providing a uniform and continuous flow of work for all trades in
direct labour force so as to avoid on the other hand the use of men
to work overtime at enhanced rate of pay to deal with periods of
excessive demands.
iii Short term programming:
This work is carried out monthly. The short term programming involves
maintenance work carried out monthly, weekly, or daily basis. In this case,
the total work load is normally allocated to some months of the year in
which work will be carried out. Where the work will be carried out. Where
the work will be carried out by outside contractors, the commencement
and completion dates should also indicate the date when the various pre-
contract processes should be initiated and completed.
2.1.7 PERMIT FOR MAINTENANCE.
28
Ralph (2016) stated that, in hand over of building from production to use, the
main points of information to be transmitted by the production personnel are:
(i) The identity of the item or items on which maintenance is needed.
(ii) There should be a clear description of the work to be done to the
assigned assets.
(iii) There should also be a statement and guarantee that all normal and
necessary precautions for the work as specified have been taken e.g.
complete isolation of the item or items from process materials electricity
service fluids, as well as the elimination of process materials.
(iv) A statement of the remaining hazards facing the maintenance facing the
maintenance workers and any special protective clothing, equipment and
precautions which he or they should use.
(v) It must be clear at this point that the nature of the work to be done
largely determines the precautions which have to be taken.
2.1.8 CAUSES OF MAINTENANCE PROBLEMS.
According to Stephen (2018) “building services rarely perform as well as
desired. The causes emanate from deficiencies in design, construction,
commissioning, tenancy work and maintenance”. Many researchers have also
observed that the generators or causes of maintenance problems could be
looked at under three main divisions.
(a) Causes initiated during the design stage.
(b) Causes initiated during the construction stage.
(c) Causes initiated during the usage stage or the users carefree
attitude (maintenance culture).
29
It is however of the opinion that all these could be planned for during
the design stage. However, unfortunately, by the provision of the normal
contract system, designers of buildings rarely have a long span interest in the
building they produced; hence, they become divorced from the maintenance
problem that follow from their bad designs. The crucial point for this work
therefore emphasizes the cause initiated during the design stage and how
planning at this stage can be employed to incapacitate other causes during
the other stages.
Maintenance problem though, do manifest during the use of building, their
causes might be during the design stage. According to Arayela and Adams
(2001) it is often said that building defects on the drawing board, but in
some cases, they can originate at an earlier stage. Inadequate brief may lay
down totally unrealistic cost limits or fail to give vital information on the
functional requirements of the building.
Design deficiencies could result in a building disaster if adequate attention
is not paid to design of bearing support, calculation errors deformation,
shrinkage problems, errors in assumed loadings (especially wind), and
changes in alteration of existing structures all these contribute substantially
to building failures and disasters. Therefore adequate attention needs to be
paid to these factors during design stage. Zubairu (2001) opined the extent
to which the various factors contribute to maintenance problems in
government office building in Nigeria is as follows; inadequate architectural
design 6% inadequate structural design 7%, inadequate electrical design 9%,
inadequate mechanical design 11%, poor construction 12%, use of poor
quality components 18%, and other 5%. According to Assaf (1996) “design
and construction faults that affect maintenance of building are in eleven
groups as follows and they could be controlled or minimized during stage”.
30
(i) Defect in civil design:
These include inadequate provision for structural movement ignoring the
effect of aggressive environment and weather conditions, ignoring biological
effects, inadequate structural design of foundations, ignoring variation in soil
conditions, ignoring load impact on structural stability etc.
(ii) Architectural defect in design:
These includes among various defect narrow stains, passages and doors, not
considering local climatic conditions for exterior shapes and material,
inadequate joints between finishes, specifying wrong finishes.
(iii) Defect due to consultant firm administration and staff:
These include lack of quality assurance and quality control during design.
(iv) Defect to construction drawing and inspection:
These include lack of references, conflicting details, lack of unqualified
inspectors and inspection.
(v) Design defects in maintenance practicability and
adequacy:
These include not considering space or exist equipment for maintenance
workers, not designing permanent fixtures which could be removed for
maintenance, etc.
2.1.9 Design Components for Maintenance Strengths.
In a recent research carried out on optimizing design processes for effective
maintenance of public building in Nigeria, twelve major factors were
identified as maintenance strengths. These the architect can be used as input
31
during design stage to prevent a minimize maintenance problems in the later
life of the building. Adejimi (2017) in such a management problem like
maintenance, such factor could be so numerous. The twelve component
therefore constitute the design inputs which are variable for determining the
maintenance strength of the buildings which can be imputed at the design
stage, these are:
i. Design resolution:
The architect needs to sincerely ask himself whether the design has been
totally resolved to suit the owners or users taste. A poorly resolved design
eventually results in serious maintenance problems. An un-detailed design
results in a poorly finished building. A poorly resolved building design does
not suit the owner and are unliveable as conversations of the functional
spaces go on daily in order to adjust to satisfy the user’s needs. This leads to
the breaking and cracking of the component parts weakening the structure
and fabric of the building.
ii. Structural strength:
Amongst all the twelve design component enumerated above, structural
strength is the only one generally taken care of by the building designers,
probably this is because of the high risk in safety when building are without
such consideration and are due to the enforcement by the planning
regulations. In adequate structural strength is building automatically lead to
failure and breakdown of its fabrics and an eventually maintainability
problem.
iii. Specified materials:
32
In durability, appropriateness, replace-ability and cost of the specified
materials and components can determine the maintainability of the building.
This is because while some materials may be durable, weatherproof,
aesthetically pleasing, and cheap, some others may be costly, unavailable for
replacement and not easily re-fixable.
iv. Maintenance manual:
If every electronic item always come with operating manual, a building which
is more costly durable and complex needs more than production blueprint
(working drawing) which most clients do not even know how to read.
Architect need to provide a maintenance manual together with the working
drawings, which includes the dos and don’ts of how to use the facility.
v. Safety measures:
Unforeseen problem like natural disaster, fire accident, earthquake, tsunamis,
etc. need to be planned for. This means that the design team needs to look
beyond the immediate to safeguard properties. If additional strength is
injected as extra into the design, this goes a very long way to protect
building at such critical periods.
vi. Skilled maintenance personnel:
Another reason why many building suffer serious maintenance problem is the
incompetence of those who are to maintain such building or unavailability of
such personnel. An extra thought on the availability of skilled personnel to
manage a proposed building before the design are finalized will go a long
way either in removing such problematic part of design or not. If there are no
skilled personnel to maintain such aspect of the building or its component
part is not available in the country, there is no need specifying such
component part.
33
vii. Maintenance plants and equipment:
Just like the skilled personnel above, there is no need to add any part of the
building of which the equipment to maintain has to be imported. The mere
fact that the equipment is not available within the country is an indicator of a
failure maintenance problem especially if you know that the country is not
industrialized enough to manufacture such equipment.
viii. Maintenance Factors:
Different buildings have to be designed differently based on their location and
environmental differences. The physical and chemical properties of materials
specified have to be weighed based on the macro and micro climatic effects
on such items in their areas of usage. The effect of weather on the specified
materials, orientation fenestration, sizes, topography, and the total
arrangement or design of the building should be one of the questions the
designers must answer at the design stage.
ix. Maintenance utility:
When all factors that lead to an effective maintenance of a building have
been taken care of, such conditions like the spaces, facilities, and the
wherewithal to make such maintenance activities easy, fast and possible are
not provided, the main problem remain.
x. Usage:
Unplanned control of the use in building has constituted one of the few
greatest maintenance problems in buildings. In this part of the word,
buildings are generally misused and at times maliciously damaged. When this
34
is well planned for, certain situations and programmes can be inputted into
the building to guide against wrong usage. This can be in form of warning,
alarm, refusal to work, or switching off (example lift system) or signal as
preventive measures.
xi. Quality control plan (workmanship):
It is at the construction stage that buildings quality and workmanship are
controlled. However, if this is not adequately planned for through proper
tendering for competent contractors, control on workmanship during
construction becomes a problem. The best way to go about this is to make a
contractor a part of the design team in which he also sees the result of the
design (i.e. the building) together as the designers and they have a common
perception of the same end product.
xii. Post construction preventive maintenance management:
In most cases, clients are not aware that there is a need for a maintenance
management of their properties. Building maintenance has to be managed.
Planning for such should not be taken lightly as a lot is involved in such
management activities. However if such management activities are not
adequately planned for there is every likelihood that a lot is neglected.
The best solution is again to make a maintenance officer a member of the
design stage has its input as an adviser to the architect. By the time the
building is completed, the maintenance officer just continues the function,
doing his job.
2.1.10 LACK OF INTEGRATION OF CONSTRUCTION PROCESSES:
One major hindrance in making maintenance free building achievable is
however the fact that our construction processes are still sequential in
nature. They are only linked at the terminal tail end of each other rather than
35
overlapping and benefiting from one another. If the design process is to be
enhanced, the building team (i.e. architect, planners, engineers, contractors
and including the clients, maintenance officers and all major actors in the
construction industries) need to come together and contribute towards the
building maintainability at the project inception rather than leaving it for the
maintenance personnel at the end of construction to battle with the creative
measures or emergency maintenance. According to Cornick (2015) the root
course of the problem that (construction) industries and its clients experience
lies in the division of the responsibilities between the design aspect and
construction aspect.
Ward (2006) was direct in his criticism of the organization of the construction
industries when he noted that the industry is unique in that the design
process is separated from production. In building, the architect design and
the contractor produce whereas in most other industries for example motor
industries, the designer is employed by the producers. The paramount aim of
both parties should go to achieve a building that will serve the client purpose
in every way, and which will present good value for money within the
limitation of time and finance available and most importantly forestalling
heavy future maintenance problems.
2.1.11 MAINTENANCE MANAGEMENT:
Efficiency and economic maintenance cannot be achieved without some
degree of organization (planning) and the rewards to be gained are well
worth the effort involved. A maintenance department duty is to ensure
maximum availability and efficiency of prosperity and equipment at maximum
economic cost and to effectively protect a large-scale investment of capital.
According to Ngoka (n.d) efficient and economic maintenance can be
achieved through the following pre-requisites.
36
(a) The provision of favourable working conditions.
(b) Careful and detailed organization.
(c) The introduction of a routine maintenance system.
(d) An initial analysis of cost and methods.
(e) Alert management.
Maintenance management is defined by Allyson (n.d) as “the selection of the
goals, planning, procurement, organization coordination and the control of
the necessary resource, for their achievement is concerned with the dynamics
of circumstances and activities and is generally initiated by need to
economize in the use of resources and times in achieving predetermine
objectives”.
Maintenance management should be able to achieve the following if properly
carried out:
(a) Economy in money material and time resource.
(b) Planned and co-ordinates maintenance programme.
(c) Use satisfaction.
(d) Efficiency of the facilities.
2.1.12 PLANNING:
“Planning is defined as the selection of future course of action through the
analysis and evaluation of possible alternatives”. This definition was given by
Obodoh (2012) and he went further to define planning of maintenance
operations as an attempt to establish the duration of time that a specified
amount of work will take having the necessary resources available and they
include:
(a) Effective planning exposes likely difficulties.
(b) Facilities the maintenance department to overcome them.
37
(c) Minimize the unproductive of both manpower and equipment.
(d) Planning focuses on the course of production of labour and
equipment needs.
(e) Useful as a control device against which progress can be measure
during and after the completion of the project.
(f) Use for forecasting material labour and equipment needs.
2.2 SUMMARY OF LITERATURE REVIEW:
As can be gathered from different or various opinion of the several
distinguish writers, the maintenance of building is very important so as to
make them sustainable, make sure the building fulfil its function, with
retaining value of money and to present good appearance. Also, maintenance
operation can simply be divided into planned and unplanned maintenance
that meets the needs for maintenance. It is recommended that building
maintenance manual should be prepared during the design stage by the
design team for easy and safe execution of maintenance works.
It is also opined that design of construction faults-defects in civil and
architectural design, defect due to construction drawings, construction
inspection unqualified inspectors lack of inspection etc. That affect
maintenance of buildings could be controlled or minimize during a design
stage. Twelve major factors that where identified previously, can be used as
input during the design stage to prevent or minimize maintenance problem in
the later life of building.
Finally, it has been gathered that maintenance of properties of both
public and private building has not been given adequate recognition due to
38
lack of integration of construction processes. And that effect, building
maintenance requires the correct diagnosis of defects and implementation of
the current removal measures, all based on sound labour and money.
CHAPTER THREE
RESEARCH METHODOLOGY
The method adopted for this research work is the quantitative research
method. This method was adopted as it has a wide coverage of the
population study in Owerri. The quantitative research method has a high rate
of acquiring information needed for the research work. It also discusses the
framework used in carrying out the research work and subsequently involves
in greater detail, the type of research method used in the study, identifies the
target population, sampling method and sample size, validation and reliability
of the instruments, method of data collection and method of data analysis.
3.1 RESEARCH DESIGN:
This deals with the methodology which is used for the purpose of this study.
It comprises of the size of the population, method of data collection and the
method data analysis. It is the way the work is drafted to give the full
information of the work being carried out.
3.2 POPULATION FOR THE STUDY AREA:
39
The target population for this research work consist of residents in Owerri
which is 200, which comprises of civil workers, private workers, consultant
and construction firms. A total of 45 copies of the questionnaire were
produced and distributed in the appropriate ratio of the population. Oral
interviews, questionnaire and field investigation were adopted.
3.3 SAMPLING TECHNIQUE:
The sampling technique chosen for this research work is the stratified
random sampling. The landlords and tenants selected in these location are
representatives of the population of all the inhabitant of in Owerri with
population of 52% of the entire population of Owerri, while the banks, fast
food restaurants and the construction/consultant company from another
group of 8%. The reason below explain why this technique was used;
(a) The landlords and tenants along the above mentioned area are quite
enormous to be sampled on after the other.
(b) The consultant and construction firms selected are reasonable to get
the required information.
3.4 SAMPLE POPULATION AND SAMPLE SIZE:
The population focused on the residents of Ikenegbu layout of Owerri and a
consultant firm in Owerri. A sample size of 45 respondents was chosen for
data analysis. They include 25 occupants of residential building in Ikenegbu
layout, including 1 of bank project manager, 1 of fast food restaurant
manager, and 15 of Natuhab consultant.
3.5 METHOD OF DATA COLLECTION:
The two main types of data collection employed in this research work are:
1. Primary data collection:
40
These are made up of information generated specially for this study as to
have a good knowledge in the research work, they include journal, lecture
notes, unpublished books etc. The data’s were collected using questionnaire,
oral interview and field investigation.
2. Secondary data collection:
They include previous and recent works form, periodicals, textbooks, etc.
3.6 INSTRUMENT FOR DATA ANALYSIS.
The tools used in this research work included the pie chart, histogram, the
percentage and chi-square test. The chi – square test gives the conclusion on
whether a set of observed frequencies differ so greatly from a set of
expected frequencies. The test was calculated from the expected frequencies.
[fe] y= [row i] x column j] ............... Equation 1
Grand total
Where [fe]ij = expected frequency for cell in the ith row and jth column.
Row jth = the total of the frequencies in the jth column
Grand total = the total of all the frequencies in the table.
41
It is the purpose of the chi-square test to provide an answer to the question
as to how great a departure from the expected frequencies can be tolerated
before the null hypothesis is rejected. The test statistic used for this
determination is “X” test.
Thus, X2 = [fo - fe] ............... Equation 2
Fe
Where; fo = observed frequency
Fe = expected frequency
X2 = chi – square test.
In order to apply the test, a certain level of confidence has to be assumed
and also the number of degree of freedom in the table determined. In
general, in a table containing “r” row and i column, there are (r – 1) (i – 1)
degree of freedom respectively.
From the chi – square (X2) distribution table determine the value of X2 in
term of an assumed level of significance.
Decision Rule:
Reject Ho if X2 calculated > X2 table.
Accept Ho if X2 calculated < X2 table.
For this research we used 0.05 or 5% level of significance.
42
CHAPTER FOUR.
DATA PRESENTATION AND ANALYSIS:
4.1 RESULTS
The results of the fieldwork and survey carried out in this work, are
presented in this section 4.1 as follows
In all, 40 questionnaires were produced and distributed to respondents, in all
questionnaires were completely filled and returned. This represented percent
rate of return.
Data were collected from the occupant in Owerri, comprising of those in
residential buildings and in the commercial building. There were a total of 40
respondents, of which the landlords and tenants were 25, including banks
and fast food restaurants, and 15 staff of Natuhab consultants.
Below are the presentation analyses of the data’s collected for each question.
Questions A: what are the maintenance problems you encounter in
building?
43
4.1.1. DEMOGRAPHIC DATA
The section A of the questionnaire was used in collecting demographic data
of the respondents. The demographic data include the age, sex, qualification,
experience of the respondents, information on the respondents, companies
were also collected. The data is presented in table 4.1
4.1.2 ANALYZING OF MAINTENANCE PROBLEMS
The data on maintenance problems are presented in table 4 and analyzed
using relative importance Index and Ranking.
The mean, X for dampness is 3.5, the mean, X score of 3.5 shows that
majority of the respondent agreed that dampness is a major cause of
deterioration.
4.1.3 CHALLENGES OF EXISTING MAINTENANCE SYSTEMS
It can be an appealing process because it seemingly offers the maximum
utilization and in turn maximum production output, of the asset by using it to
its limits. This strategy is only beneficial, however, up until the point where
the asset fails. Preventing failures of assets under load, however, has been
proven to be far more cost-effective with the same production output.
It is a widely accepted industry fact that a well-planned and scheduled
corrective Work Order is about three to four times less expensive than the
same unplanned reactive Work Order.
Organizations utilizing this reactive maintenance strategy/ approach often fall
victim to treating the asset symptom, rather than the problem causing the
symptom.
44
When maintenance moves from a reactive to a planned environment, there is
less wasted time and effort looking for the right part and getting instructions.
As a result, there is less confusion around who is doing what and when. Also,
the repairs can be coordinated with production resulting in quicker
turnarounds since the assets will not be under load when the repair starts.
Imagine the craft productivity that could be attained if your technicians go
straight to the job and straight to work, rather than spending the first hour or
two searching for a plan of action or having production clearing out the
equipment before work can start.
i. Difficult to Control Budgets
As equipment failures can be unpredictable, labor and spare parts may not be
readily available, so organizations may end up paying a premium for
emergency parts shipping, travel time and out of hours support. It is
therefore difficult to accurately budget for maintenance and to provide proper
forecasts of when budgets will be spent.
ii. Shorter Life Expectancies of Assets
Reactive maintenance does not keep the systems running in optimal “as new”
condition. Over time, systems that have been maintained reactively,
deteriorate faster due to related induced failures and therefore do not
maximize their initial capital cost investment. This negatively impacts a
company’s RONA (Return on Nett Assets) which in return reduces
shareholder value.
iii. Safety Issues
When work is properly scheduled, technicians have time to review the
standard procedures and safety requirements to complete the job correctly.
Technicians tend to take more risks when maintenance work is reactive as
they are under pressure to get systems running without delay. Most
45
companies have Safety and Health as one of their strategic objectives and a
reactive / breakdown approach goes directly against this objective.
iv. Time-consuming
Reactive repairs tend to take longer due to several factors including time to
diagnose, travel time, time to pull parts from stores or submitting emergency
orders, time to pull correct manuals and schematics… etc. This, therefore,
impacts the ability of the production teams to achieve their production
targets and depending on which equipment fails can have a negative impact
on revenue.
v. Sporadic Equipment Downtime
Planned maintenance can be written into the production schedule whereas
unplanned repairs can happen anytime. Also, there is the uncertainty around
the length of delay due to the unplanned repair. Equipment that
often/sporadically breaks down reduces the trust between maintenance and
production.
vi. Inefficient Use of Resources
Technicians spend time running around looking for the correct manuals and
schematics, ordering the right parts, etc. and trying to diagnose and fix the
issue. Often, they need to wait for equipment to be cleared and permits to be
issued. In essence, companies pay for their resources (technicians, special
tools, equipment, etc.) to be productive and all waiting times comes at a high
cost to organizations.
vii. Interferes With Planned Preventive Work
Emergency repairs are usually prioritized at the expense of planned
preventive work. Planned work may be pushed or canceled completely
resulting in future unexpected failures that will result in additional unplanned
46
work and future preventive work being missed. This is what is called the
maintenance death spiral.
viii. Collateral Damage
A minor issue could quickly turn into a major system repair. For example, if
your car’s engine is low on oil, it could result in warn cylinders or damage to
seals, but ultimately in a completely seized engine. Or the slight
misalignment of a shaft not only damages the bearing but over time can
result in a cracked or seized gearbox or even damage to the shaft itself.
ix. Indirect Costs
Unplanned downtime can lead to late orders if equipment cannot be returned
to production in time. This can damage reputations and impact revenues.
Persistent non-delivery or late delivery of orders can have the knock-on effect
that key customers lose confidence in the organization and may go to other
suppliers or demand discounts/ raise penalties which can cost the
organization millions.
x. Repeat Issues
Reactive maintenance does the bare minimum to get the system up and
running again, due to the pressure to return the plant back to production. If
not repaired correctly soon after (and typically this rarely happen), the issue
could reoccur and cause more downtime. A very negative downward spiral.
xi. Higher Energy Costs
If you don’t service your car, it burns more fuel! When equipment is not
properly maintained, it uses more energy. Doing simple things like greasing
moving parts or changing filters can reduce energy consumption by up to
15%.
47
Repairing damaged equipment quickly is important for minimizing downtime.
Relying on a reactive maintenance strategy, in most cases, is, therefore, an
inefficient and very costly way to operate. Emergency repairs cost as much as
5 to 7 times more than planned preventive work, which can obviously have a
huge impact on the bottom line.
Maintenance problems encountered by the occupants.
Problems Frequency of Responses % responses
Dampness of wall 17 68%
And floors
Leaking roofs 8 32%
Blockage in pipes 1 48%
(Toilet & kitchen)
Spilling of fees from 11 44%
Septic tank
Flooding around 14 56%
Compound
Non–functioning/ 38 72%
48
Blocked drainages
Workmanship 22 44%
Problems
Waste disposal 28 72%
Table 4.1
Source: field survey 2024
The above data is analysed using the percentage data analysis method.
Dampness of walls and floors: from the analysis above only 68% of the
population of the occupants has this maintenance problem.
Leaking roof: Only 32% of the total population has this problem of roof
leaking.
Blockage of pipes (toilet & kitchen): 48% of the total population are
affected by this problem.
Spilling of fees from septic tank: from the analysis only 44% of the
population has this problem.
Flooding around compound: 56% of the population has the problem of
flooding in the compound.
Non – functioning / blocked drainage system: 72% of the population
has this problem. This shows that only a few of the population is not affected
by this maintenance problem.
Workmanship problem: from the analysis 44% of the total population is
affected by the problem.
Waste disposal: A high percentage of 72% of the population is having a
problem of waste disposal which is maintenance problem.
49
Question B: How are damaged parts repaired in the building?
Respondents No. of respondent
Repaired of tenants 17
Repaired by tenants and deducted
from their rents
6
Repaired by landlords 2Source: field survey 2024
Table 4.1:
Showing how buildings are repaired by occupants.
17-
16-
15-
14-
13-
12-
11-
10-
9-
8-
7-
6-
5-
4-
3-
2-
1-
0-
50
Source: field survey 2024
= Repaired by tenants
= Repaired by tenants and deducted from rents
= Repaired by Landlord.
The data above is analyzed using the Bar chart shown below:
Fig. 4.0:
Bar chart showing the degree of repair by tenants and landlords
Question C: How do you respond to the repair of damaged parts in
building?
Response to repair No. of respondents
Repair only when the it is not usable
(corrective maintenance)
20
Repair when it is faulty 5Source: field survey 2024
Table 4.2:
Showing the building repair response
The data above is analyzed using the percentage data analysis below
Response to Repair No. of Response % of response
Repair only when its not
usable(corrective
maintenance)
25 82.5%
Repair when its faulty 5 16.5%Source: field survey 2024
Table 4.3
Showing Percentage of response to repair by occupants
51
From the analysis above it shows that 82.5% of the population of the
occupants in Owerri uses the corrective type of maintenance, which is the
repair done when the component is no longer reliable for its designed
services. This population consists of mostly civil servants.
The 16.5% of the population which mostly the commercial buildings has the
16.5% which uses the preventive type of maintenance.
Question D: Can the following factors lead to bad maintenance?
A questionnaire directed to the occupants in Owerri (O.) and consultants
s/n Questionnaires Strongly
Agreed
Agreed Fairly
Agreed
Disagreed
1. Nonchalant attitude of property
owners
Consultants 8 5 ------- 2
Occupants of I.L 10 7 5 3
2. High cost of building materials
Consultants 3 7 3 2
Occupants of I.L 11 10 3 1
3. Ignorance/ illiteracy
Consultants 4 3 4 4
Occupants of I.L 7 5 3 10
4. Inadequate finance
Consultants 10 5 -------- ---------
Occupants of I.L 15 10 ------- ---------
5. Bad usage of properties
Consultants 6 5 1 3
52
Occupants of I.L 10 8 4 3
6. Poor design and construction
Consultants 8 4 ------ 3
Occupants of I.L 5 9 2 9
7. Unnecessary/ complex design
Consultants 5 4 4 2
Occupants of I.L 7 6 2 10
8. State of National economy
Consultants 13 ----- ------- 2
Occupants of I.L 10 10 2 3
4.2 DISCUSSING OF RESULT
This research work was conducted to know the state maintenance role
of side case study. Prior to this, in chapter one this work has aim for
carrying out this work which includes;
(a) Examining the problems of maintenance, of which the data were
collected using oral interview and was presented and analyzed in
chapter four to include the following; leaking roofs, dampness of
the walls and floors, blockages in pipes, spilling of feces from
septic tanks, waste disposal problems etc. These maintenance
problems were tabulated and presented using table as shown in
table 4.0 and analyzed using the percentage of the population
having this maintenance problems.
(b) Investigate the influence of neglect of maintenance of buildings
and on the occupants, which the data were collected through field
53
investigation presented at the appendix to include; cracks on
walls, peeling of paints on walls caused by dampness, non
functioning of the drainage systems etc.
Further works were carried out to know the problems behind poor
maintenance role of the occupants of Ikenegbu layout of which a
good maintenance role lies on the repair and response to repair
of the buildings, so works were done to know the problems
behind delay in repair. Table 4.1 shows how buildings are
repaired and a bar chart was used to analyze the work, which
shows the number of occupants involved in repair and how the
repair is done.
Table 4.2 showed the response to repair attitude of the resident
of the case study while table 4.3 showed percentage of response
to repair by occupants. From the analysis of table 4.3, it showed
that 82.5%of the population of ikenegbu layout uses corrective
type of maintenance, which is the repair done when the
component is no longer usable, 16.5% of population which
comprise mostly the commercial buildings uses the preventive
type of maintenance.
The last work done on this project was the testing of the
hypothesis raised in chapter one of which the null (Ho) stated
that, the present state of the national economy have a significant
effect on maintenance roles. Data were collected from te
occupants and from the consultants to establish basis from the
test. From the questionnaire distributed, response were received
from both groups of respondents. Table 4.4 shows the
distribution of questionnaires among the occupants of Ikenegbu
layout and consultants. Table 4.5 shows the observed frequency
of the two groups explaining their responses on the question
54
which was used to establish basis for the hypothesis postulated in
chapter one.
Table 4.6 shows the expected frequency of the respondents with
equation 3 given the formula for the computation of the expected
frequency. Table 4.7 shows the computation of chi-square (X2).
From the table, X2 calculated = 0.41 and X2 =3.84.
Decision rule states accept Ho if X2C