GAS LIFTING DESIGN USING CONTINUOUS GAS LIFTING METHOD: A CASE STUDY OF NPDC WELL 22L IN PTIX FIELD
Abstract
ABSTRACT
This project focuses on the gas lift design and performance analysis of
Well 22L, located in the PTIX field with a reservoir depth of 9,000 ft. The
study evaluates the well's initial production parameters, reservoir
characteristics, and subsequent performance enhancements through a
staged gas lift system. With a reservoir pressure of 2,500 psi, a
productivity index of 9.0 STB/D/psi, and a target production rate of 3,000
BOPD, the well's gas lift process was optimized by strategically placing 12
valves at depths ranging from 2,100ft to 7,600ft. The first valve, which
should be installed at depth 2100ft known as the kick off valve, initiates
production by displacing fluids and reducing hydrostatic pressure, while
subsequent valves, known as unloading valve maintain tubing pressure
and the last valve, known as the operating valve should be installed at
depth 7600ft, ensure efficient gas injection. The volume of gas needed to
achieve 3000BOPD production rate was obtained as 960,000 SCF
(960mscf/d) (320 SCF/bbl × 3,000 BOPD). The project highlights the
impact of gas lift on stabilizing flow conditions, minimizing operational
costs, and extending well productivity despite declining reservoir
pressure. A comparative analysis of initial and current performance
revealed significant improvements in flowing bottom hole pressure,
stabilized production rates, and reduced gas injection costs.